Brookfield Project

Clients Request: Construct a 65 metre x 25 metre arena & cut a shed pad 

 

This job was completed over 3 stages.

​

Stage One:

Clearing & stump removal of a macadamia & mango plantation.

 

Stage Two:

Bulk Earthworks: Cut the 65m x 25m arena pad & 65m x 35m shed pad. This required use of the dozers, padfoot roller, water cart & posi tracks. In addition to cutting the pads, we also constructed a secondary access road around the property boundary which included the installation of a twin concrete pipe crossing across the dam spill way.

 

Stage Three:

 Completing laser levelled arena surface & installing road base on the 250m secondary access road.

​

This job came with many challenges that the All Aspects Earthworks had to overcome and work around. The biggest challenge was the property had a old timber bridge that was the only access for all materials. This required an engineer report & came back with a max weight of 20T to be brought across. To get all materials into the job this required the reloading of 1300T of road base, crusher dust & arena sand into 8t tippers.

262789935_247746707285190_2753780319769815554_n.jpg
261417746_329076941998825_8650221409274371168_n.jpg
261452005_4419099528209095_7352476335923639077_n.jpg
262309480_618610435998346_6344079827817709644_n.jpg

3 Armstrong Creek Rd, Armstrong Creek QLD 4520

All Aspects Earthworks Pty Ltd - ABN: 68633178702

bottom of page