Bunya Springs Project

Clients Request: Create an access road, 70 metre x 30 metre arena, turn around area & storage pad

 

This job was completed over 2 stages.

 Stage One:

Clearing & removal of trees & bulk earthworks to make room for the new driveway. Cut & filling a turn around area,  shed pad, & laser levelling a 70m x 30m pad ready for a full size arena. This job was completed with our dozer, roller, water cart & 5T combo.

 

Stage Two:

Installation of road base along the new driveway, turn around area & shed pad. This also included the full surface installation of the 70m x 30m dressage arena.